Building Developments Update 5 (BDU5)


19 June 2018

 

Armfield Academy – Building Developments Update 5 (BDU5)

Date: Tuesday 19th June 2018

 

 

“Welcome to our fifth BDU which gives readers an insight into the building developments currently taking place on the academy sites to the north and south of Arnold Avenue. 

The South Buildings will be ready in time for our September 2018 intake of 160 Year 7 students, 60 Reception students and the Nursery children.  The bullet points below identify what specific actions are currently underway and what will follow. 

Please see the architectural elevations on BDU1 (please click latest news) of how our fantastic new Armfield Academy will look.  I intend to post further regular BDUs with photographs on a monthly basis.  Thank you for your continued support”.

John Topping, FCAT Community Relations and Estates Lead

Email – jt@fcat.org.uk

Please click on each of the images below for individual details


Armfield BDU 5


  • Head of School Mark Kilmurray welcoming us to the South Buildings
  • South Buildings classrooms all wired up to receive the teaching wall whiteboards, all plumbing completed, suspended ceilings being fitted along with overhead radiant heat panels.
  • All classrooms and open spaces in the South Buildings receiving the appropriate vinyl or carpet floor covering.
  • Dining Hall ceiling receiving its first coat of black polymer paint, walls receiving the first coat of paint.
  • Across Arnold Avenue into the North Buildings zone – the Sports Hall and Memorial Hall walls being plastered – ready for opening in September 2019.
  • Main North Building steel structure growing by the day, internal brick walls already being constructed – ready for September 2019.
  • Main North Building steel structure growing by the day, internal brick walls already being constructed – ready for September 2019.
  • Main North Building steel structure growing by the day, internal brick walls already being constructed – ready for September 2019.